Golden Pass LNG asks US regulator for 3-year extension to complete construction



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Golden Pass LNG asks US regulator for 3-year extension to complete construction</title></head><body>

Adds Golden Pass comment on startup timing in paragraph 4

HOUSTON, Aug 29 (Reuters) -The developer of a Texas liquefied natural gas export project on Wednesday asked U.S. regulators for a three-year extension to complete construction ofthe $10 billion Golden Pass LNG project, citing scheduling uncertainties.

Golden Pass LNG, a joint venture of QatarEnergy QATPE.UL and Exxon Mobil XOM.N building an 18 million metric ton per annual LNG export project on the Texas coast, wrote that a change in primary contractors requires an extension until November, 2029.

Exxon and QatarEnergy this month said the project startup would be delayed until late next year. The current approval expires in November 2026 and the request signals a later startup.

The company's "goal is to produce first LNG around the end of 2025 with commercial operations following thereafter," a Golden Pass LNG spokesperson said. "The extensions we have requested build in time for contingencies."

QatarEnergy owns 70% of the joint venture and Exxon the remainder.

"The additional time will allow for the rehiring and remobilization of over 4,000 skilled workers and provide for potential uncertainties such as severe weather or hurricane delays when it may not be safe to have crews on site," Golden Pass LNG wrote the Federal Energy Regulatory Commission.

In May, Zachry Industrial, which was the primary contractor for the project, filed for bankruptcy after a dispute over $2.4 billion in cost overruns. Golden Pass LNG subsequently named CB&I, a unit of McDermott International MCDIF.PK, as lead contractor.

Golden Pass LNG is seeking the additional three-year period under a FERC provision that allows an extension if a company can show it made good faith efforts to complete a project on time, it said in a letter to FERC.

Construction of the first gas-processing unit is approximately 83% complete, and the second and third processing units are 46% and 31% complete, respectively, the FERC filing said.



Reporting by Gary McWilliams
Editing by Marguerita Choy

</body></html>

Javobgarlikdan voz kechish: XM Group korxonalari har biri faqat ijro xizmatlarini koʻrsatadi va onlayn savdo platformamizdan foydalanish huquqini beradi, bu odamga veb-saytda yoki veb-sayt orqali mavjud boʻlgan kontentni koʻrish va/yoki undan foydalanishga ruxsat beradi hamda uni oʻzgartirishga moʻljallanmagan va uni oʻzgartirmaydi yoki kengaytirmaydi. Bunday kirish va foydalanish huquqi doimo quyidagilarga boʻysunadi: (i) Shartlar va qoidalar; (ii) Risklar haqida ogohlantirish; va (iii) Javobgarlikni toʻliq rad etish. Shuning uchun bunday kontent umumiy maʼlumot sifatida taqdim etiladi. Xususan, shuni esda tutingki, bizning onlayn savdo platformamiz mazmuni moliyaviy bozorlarda biror bitimni amalga oshirishga oid maslahat yoki taklif emas. Har qanday moliyaviy bozorda savdo qilish sizning kapitalingiz uchun jiddiy risk darajasini oʻz ichiga oladi.

Onlayn savdo platformamizda chop etilgan barcha materiallar faqat taʼlim/axborot maqsadlari uchun moʻljallangan va unda moliyaviy, investitsiya soligʻi yoki savdo maslahatlari va tavsiyalar; yoki bizning savdo narxlarimizning qaydlari; yoki har qanday moliyaviy vositalar bilan bitim tuzish maslahati yoki taklifi; yoki sizga kerak boʻlmagan moliyaviy reklama aksiyalari hisoblanmaydi

Har qanday uchinchi tomon kontenti, shuningdek XM tomonidan tayyorlangan kontent, masalan: fikrlar, yangiliklar, tadqiqotlar, tahlillar, narxlar va boshqa maʼlumotlar yoki bu veb-saytda joylashgan uchinchi tomon saytlariga havolalar umumiy bozor sharhi sifatida "boricha" taqdim etiladi va investitsiya maslahatini tashkil etmaydi. Har qanday kontent investitsiya tadqiqoti sifatida talqin qilinsa, siz bunday kontentni investitsiya tadqiqotlarining mustaqilligini ragʻbatlantirish uchun moʻljallangan qonun talablariga muvofiq moʻljallanmagan va tayyorlanmaganligini eʼtiborga olishingiz va qabul qilishingiz kerak, shuning uchun unga tegishli qonunlar va qoidalarga muvofiq marketing kommunikatsiyasi sifatida qaraladi. Mustaqil boʻlmagan investitsiya tadqiqoti va yuqoridagi maʼlumotlarga oid risk haqida ogohlantirishimizni oʻqib chiqqaningizga va tushunganingizga ishonch hosil qiling, unga bu yerdan kirish mumkin.

Riskdan ogohlantirish: Kapitalingiz risk ostida. Kredit yordamiga ega mahsulotlar hammaga ham toʻgʻri kelmasligi mumkin. Bizning Risklardan ogohlantirishimiz bilan tanishib chiqing.