US utilities signal booming demand from data centers as AI takes root



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>FACTBOX-US utilities signal booming demand from data centers as AI takes root</title></head><body>

Aug 12 (Reuters) -U.S. utilities are finally inking concrete supply deals with data-center operators hungry for more power amid a boom in artificial intelligence, paving the way for higher sales and profit in the coming quarters.

Data centers are expected to account for 8% of the power generated in the U.S. by 2030, compared with 3% in 2022, according to a Goldman Sachs report in May.

Here are some deals announced by utilities in 2024:


Ameren AEE.N signed a supply deal with a data center with a power capacity of 250 megawatt (MW). It has also received expansion commitments and executed new contracts for more 85 MW of additional load for smaller data centers and other industries across Missouri and Illinois.


Alliant Energy LNT.O said it has executed multiple power supply deals with data centers, but did not disclose details.


Exelon EXC.O said it is in the engineering phase for more than 5 GW of data center capacity. Some data-center customers have also made deposits for ComEd - Exelon's subsidiary - to order transmission and breakers, the firm said during a post-earnings call.


American Electric Power AEP.O signed letters of intent to power an additional 15 GW of data centers by the end of the decade.


Xcel Energy XEL.O will supply power to Meta Platforms' META.O data center in Minnesota, expected to come online in late summer 2025.


Entergy ETR.N has received legislative approval for investment in transmission and generation to serve Amazon's AMZN.O upcoming Amazon Web Services (AWS) facility in Mississippi.

Pinnacle West Capital PNW.N has more than 4,000 MW of committed data center customers, not including the backlog of more than 10,000 data center requests it has received.


AES AES.N signed an agreement with Google GOOGL.O for 310 megawatts to support its Ohio data centers.

It further expanded a previously announced partnership with Google and signed a 15-year power purchase agreement for 727 megawatts in Texas.


Talen Energy TLN.O announced a deal to supply electricity and its 960-megawatt data center campus to Amazon's AWS in Pennsylvania.


NextEra's renewables segment saw a rise of 3 gigawatts (GW) worth of renewables and storage projects in second quarter, including Google's 860 megawatts (MW) demand for its data center power.



Reporting by Vallari Srivastava in Bengaluru; Editing by Sriraj Kalluvila

</body></html>

免責聲明: XM Group提供線上交易平台的登入和執行服務,允許個人查看和/或使用網站所提供的內容,但不進行任何更改或擴展其服務和訪問權限,並受以下條款與條例約束:(i)條款與條例;(ii)風險提示;(iii)完全免責聲明。網站內部所提供的所有資訊,僅限於一般資訊用途。請注意,我們所有的線上交易平台內容並不構成,也不被視為進入金融市場交易的邀約或邀請 。金融市場交易會對您的投資帶來重大風險。

所有缐上交易平台所發佈的資料,僅適用於教育/資訊類用途,不包含也不應被視爲適用於金融、投資稅或交易相關諮詢和建議,或是交易價格紀錄,或是任何金融商品或非應邀途徑的金融相關優惠的交易邀約或邀請。

本網站的所有XM和第三方所提供的内容,包括意見、新聞、研究、分析、價格其他資訊和第三方網站鏈接,皆爲‘按原狀’,並作爲一般市場評論所提供,而非投資建議。請理解和接受,所有被歸類為投資研究範圍的相關内容,並非爲了促進投資研究獨立性,而根據法律要求所編寫,而是被視爲符合營銷傳播相關法律與法規所編寫的内容。請確保您已詳讀並完全理解我們的非獨立投資研究提示和風險提示資訊,相關詳情請點擊 這裡查看。

風險提示:您的資金存在風險。槓桿商品並不適合所有客戶。請詳細閱讀我們的風險聲明