By Marianna Parraga and Curtis Williams

HOUSTON, July 18 (Reuters) -The number of liquefied natural gas (LNG) tankers waiting to load at Freeport LNG in Texas has increased since the U.S. second largest exporter of the supercooled gas halted processing ahead of Hurricane Beryl's landfall last week, according to shipping data on Thursday.

Beryl made landfall on July 8 near Matagorda, on the Texas coast, lashing the state with 80-mph (130-kph) winds that caused infrastructure damages and left more than 2 million customers without electricity for days.

Ports and energy companies in many coastal cities, including Freeport, suffered wind damage and slow restoration of power.

Freeport LNG, which shut its three liquefaction trains on July 7 and reported wind damage after, has had a slow operational restart since.

The LNG exporter said on Monday it planned to restart one processing train this week and the remaining two trains shortly after, but production would be reduced while it continued repairs.

U.S. gas futures NGc1 had dropped about 7% on Monday to a 10-week low after it became clear to the market that Freeport LNG would likely continue to operate at less than full capacity for several more days.

On Thursday, feedgas to the facility was risingwith it expected to use 500 million cubic feet, up from 400 mmcf on Wednesday, according to LSEG data. The gas utilization increase is seen as an indicator of LNG production starting in the first train, which can use up to 700 mmcf per day.

However, vessel loading has not resumed. A total of six empty LNG tankers were anchored near the port, compared with a couple ships before the storm, with some of them accumulating more than 10 days of wait. Last loaded vessels before Beryl's landfall departed Freeport on July 5, according to LSEG.

As of Thursday, Freeport LNG had not distributed any instruction to bring tankers into its berths, even though there were some vessels in schedule, a source familiar with the company's operations said.

The Port of Freeport last week reopened the navigation channel, but draft restrictions for vessels remain, the Brazos Pilots Association said.

Long waits for vessels that have back-to-back contracts tend to lead to cargo cancellations.

Freeport LNG has canceled at least 10 cargoes for loading through August, Bloomberg reported, citing traders familiar with the matter.

Freeport LNG said on Thursday it would not comment on its commercial activity, including cargoes.

Gas flows to the seven big U.S. LNG export plants has fallen to 11.6 billion cubic feet per day (bcfd) so far in July due mostly to the Freeport outage, down from 12.8 bcfd in June and a monthly record high of 14.7 bcfd in December 2023.




US natgas prices climb 4% on small storage build, hot weather forecasts nL1N3JA0N2


Reporting by Marianna Parraga, Curtis Williams and Arathy Somasekhar
Editing by Marguerita Choy

</body></html>

免責聲明: XM Group提供線上交易平台的登入和執行服務,允許個人查看和/或使用網站所提供的內容,但不進行任何更改或擴展其服務和訪問權限,並受以下條款與條例約束:(i)條款與條例;(ii)風險提示;(iii)完全免責聲明。網站內部所提供的所有資訊,僅限於一般資訊用途。請注意,我們所有的線上交易平台內容並不構成,也不被視為進入金融市場交易的邀約或邀請 。金融市場交易會對您的投資帶來重大風險。

所有缐上交易平台所發佈的資料,僅適用於教育/資訊類用途,不包含也不應被視爲適用於金融、投資稅或交易相關諮詢和建議,或是交易價格紀錄,或是任何金融商品或非應邀途徑的金融相關優惠的交易邀約或邀請。

本網站的所有XM和第三方所提供的内容,包括意見、新聞、研究、分析、價格其他資訊和第三方網站鏈接,皆爲‘按原狀’,並作爲一般市場評論所提供,而非投資建議。請理解和接受,所有被歸類為投資研究範圍的相關内容,並非爲了促進投資研究獨立性,而根據法律要求所編寫,而是被視爲符合營銷傳播相關法律與法規所編寫的内容。請確保您已詳讀並完全理解我們的非獨立投資研究提示和風險提示資訊,相關詳情請點擊 這裡查看。

風險提示:您的資金存在風險。槓桿商品並不適合所有客戶。請詳細閱讀我們的風險聲明