NextDecade to appeal court's overturning of Rio Grande LNG project authorization



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-NextDecade to appeal court's overturning of Rio Grande LNG project authorization</title></head><body>

Rewrites throughout, adds stock information, plan to appeal and risks to access to funds if it does not hold its permits

Aug 14 (Reuters) -U.S. liquefied natural gas (LNG) developer NextDecade NEXT.O said on Wednesday it will appeal a court ruling that overturned federal approval for its $18 billion Rio Grande LNG project and warned loss of its permits could prevent access to its loans.

"Its ability to continue borrowing under such credit facilities could be negatively impacted," Next Decade told the market.

The company's stock price has slumped 38% since the judgment, finishing at $4.84 on Wednesday down from its close on Aug. 5.

NextDecade said there is no guarantee how long any agency proceedings and judicial challenges will take to be resolved, if there will be delays in construction activities or if Rio Grande will ultimately succeed in maintaining the permits.

The judicial decision would not come into effect until the court issued a mandate, which was not expected to occur until the appeals process has been completed, NextDecade said.

"If the ruling stands, the precedent set impacts the viability of all federally permitted infrastructure projects because it will be difficult for developers to attract capital investments until projects receive final unappealable permits," CEO Matt Schatzman said.

Next Decade's flagship facility has been in development for several years and has already suffered repeated delays.

The first phase of the project, with a capacity of 17.61 million tons per annum (MTPA), is due to be completed by early 2029 at an expected cost of about $18 billion.

The company, backed by the likes of Global Infrastructure Partners and French energy major Total Energies TTEF.PA, said that overall project completion of the first two liquefaction units, called trains, stands at 24.1%, as of June.

It has received purchase orders of about 92% of total capacity for the first two trains and 88% of the total for the third train.

The company was planning to start construction of the fourth train in the second half of 2024 after a final investment decision and said it is assessing the implications of the court ruling with its equity partners and lenders.




Reporting by Sourasis Bose in Bengaluru and Curtis Williams in Houston; Editing by Mohammed Safi Shamsi and Sonali Paul

</body></html>

免責聲明: XM Group提供線上交易平台的登入和執行服務,允許個人查看和/或使用網站所提供的內容,但不進行任何更改或擴展其服務和訪問權限,並受以下條款與條例約束:(i)條款與條例;(ii)風險提示;(iii)完全免責聲明。網站內部所提供的所有資訊,僅限於一般資訊用途。請注意,我們所有的線上交易平台內容並不構成,也不被視為進入金融市場交易的邀約或邀請 。金融市場交易會對您的投資帶來重大風險。

所有缐上交易平台所發佈的資料,僅適用於教育/資訊類用途,不包含也不應被視爲適用於金融、投資稅或交易相關諮詢和建議,或是交易價格紀錄,或是任何金融商品或非應邀途徑的金融相關優惠的交易邀約或邀請。

本網站的所有XM和第三方所提供的内容,包括意見、新聞、研究、分析、價格其他資訊和第三方網站鏈接,皆爲‘按原狀’,並作爲一般市場評論所提供,而非投資建議。請理解和接受,所有被歸類為投資研究範圍的相關内容,並非爲了促進投資研究獨立性,而根據法律要求所編寫,而是被視爲符合營銷傳播相關法律與法規所編寫的内容。請確保您已詳讀並完全理解我們的非獨立投資研究提示和風險提示資訊,相關詳情請點擊 這裡查看。

風險提示:您的資金存在風險。槓桿商品並不適合所有客戶。請詳細閱讀我們的風險聲明