Czechs pick South Korea's KHNP over French bid in nuclear power tender



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 3-Czechs pick South Korea's KHNP over French bid in nuclear power tender</title></head><body>

South Korea's KHNP preferred to France's EDF

KHNP to build two new units, more possible

Prague plans to sign deal with KHNP in Q1 next year

For a FACTBOX on KHNP's winning bid, click here

Adds electricity price detail, KHNP comment, background in paragraphs 5, 9-12, 19

By Jason Hovet

PRAGUE, July 17 (Reuters) -The Czech government on Wednesday picked South Korea's KHNP to build two new nuclear power units, with the possibility of more, after a lengthy tender aimed at keeping a big role for nuclear power in the country's energy mix for decades.

Korea Hydro & Nuclear Power (KHNP) was picked over rival French bidder EDF, despite lobbying for EDF from French President Emmanuel Macron.

Prague earlier this year widened the tender, which is run by 70%-state-owned energy company CEZ CEZP.PR, to have the option to build multiple units, up from an originally planned one.

Under the plans, KHNP will build two new units at CEZ's Dukovany nuclear plant, and they will discuss an option for two more units at the Temelin power station.

The price for one new unit when building two at the same site was estimated at 200 billion crowns ($8.65 billion) at current prices, the government said, adding it suggested the price of electricity generated would be less than 90 euros per megawatt hour (MWh).

Contract details will be worked out by the first quarter next year before being signed, officials said.

"The Korean offer was better practically in all assessed criteria," Czech Prime Minister Petr Fiala told a news conference.

"We will build two blocks at Dukovany, and in this direction there will be negotiations. And we will discuss about options for another two blocks at Temelin about which we will be able to decide in the future."

KHNP has helped put several new reactors online in recent years, including the Arab world's first nuclear power plant in the United Arab Emirates. The Czech deal will offer another foothold in Europe.

In 2022, KHNP agreed with a Polish consortium to develop new nuclear reactors but that project is still uncertain.

KHNP CEO Whang Joo-ho said in a statement the company would enter final negotiations to "ensure that the APR1000 reactor is actually built in the Czech Republic", referring to its reactor model.

EDF, Europe's only builder of nuclear reactors. has not completed construction of a new unit since 2019 amid project delays.

The decision represented another setback for the French nuclear sector after Poland, in a separate deal, chose Westinghouse over EDF for a plant on the Baltic Sea in 2022.


NUCLEAR POWER EXPANSION

The Czech government had the final decision on the tender due to national security considerations and cost, which is too high for CEZ - even with a market capitalisation of $20.1 billion - to shoulder alone.

The central European country will lean more on nuclear power as it phases out coal in the coming decade. Nuclear is seen composing half the country's generation mix in the future, up from around a third now.

CEZ aims to start construction of the first new unit at Dukovany later this decade, with expected completion in 2036.

The government and CEZ widened the tender's scope to help lower the price of each block in what is expected to be the country's largest energy investment to date.

CEZ has agreed a financing model with the government for the first new unit at Dukovany, including low-interest loans and a scheme for pricing of produced electricity - called a contract for difference - to guarantee CEZ a return.

The European Commission has given approval to the state aid for the first unit and will still have to sign off on aid plans for further units. The Czech Finance Ministry aims to have a financing model for further units agreed by the end of the year.

($1 = 23.1240 Czech crowns)



Reporting by Jason Hovet in Prague, Joyce Lee in Seoul and Benjamin Mallet and Dominique Patton in Paris; Editing by Mark Potter

</body></html>

免責聲明: XM Group提供線上交易平台的登入和執行服務,允許個人查看和/或使用網站所提供的內容,但不進行任何更改或擴展其服務和訪問權限,並受以下條款與條例約束:(i)條款與條例;(ii)風險提示;(iii)完全免責聲明。網站內部所提供的所有資訊,僅限於一般資訊用途。請注意,我們所有的線上交易平台內容並不構成,也不被視為進入金融市場交易的邀約或邀請 。金融市場交易會對您的投資帶來重大風險。

所有缐上交易平台所發佈的資料,僅適用於教育/資訊類用途,不包含也不應被視爲適用於金融、投資稅或交易相關諮詢和建議,或是交易價格紀錄,或是任何金融商品或非應邀途徑的金融相關優惠的交易邀約或邀請。

本網站的所有XM和第三方所提供的内容,包括意見、新聞、研究、分析、價格其他資訊和第三方網站鏈接,皆爲‘按原狀’,並作爲一般市場評論所提供,而非投資建議。請理解和接受,所有被歸類為投資研究範圍的相關内容,並非爲了促進投資研究獨立性,而根據法律要求所編寫,而是被視爲符合營銷傳播相關法律與法規所編寫的内容。請確保您已詳讀並完全理解我們的非獨立投資研究提示和風險提示資訊,相關詳情請點擊 這裡查看。

風險提示:您的資金存在風險。槓桿商品並不適合所有客戶。請詳細閱讀我們的風險聲明