Corrosion exceeds estimates at Michigan nuclear plant US wants to restart, regulator says



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Corrosion exceeds estimates at Michigan nuclear plant US wants to restart, regulator says</title></head><body>

Adds Holtec comment

By Timothy Gardner

WASHINGTON, Oct 2 (Reuters) -Holtec, the company wanting to reopen the Palisades nuclear reactor in Michigan, found corrosion cracking in steam generators "far exceeded" estimates, the U.S. nuclear power regulator said in a document published on Wednesday.

President Joe Biden's administrationthis week finalized a $1.52 billion conditional loan guarantee to the Palisades plant. It is part of an effort to support nuclear energy, which generates virtually emissions-free power, to curb climate change and to help satisfy rising electricity demand from artificial intelligence, electric vehicles and digital currency.

Palisades, which shut under a different owner in 2022, is seeking to be the first modern U.S. nuclear power plant to reopen after being fully shut.

A summary of an early September call between the U.S. Nuclear Regulatory Commission and Holtec published on Wednesday said indications of stress corrosion cracking in tubes in both of Palisade's steam generators "far exceeded estimates based on previous operating history." It found 1,163 steam generator tubes had indications of the stress cracking. There are more than 16,000 tubes in the units.

Steam generators are sensitive components that require meticulous maintenance and are among the most expensive units at a nuclear power station.

Holtec wants to return the plant to operationlate next year. Patrick O'Brien, a company spokesperson, said the results of the inspections "were not entirely unpredicted" as the standard system "layup process", or procedure for maintaining the units, was not followed when the plant went into shutdown.

But he said the return of Palisades is still on schedule and that Holtec wants to fix, and not replace, the steam generators, which he said would last for 30 years after repairs.

"We expect the repair strategy will be to 'unplug' approximately 300 tubes per steam generator that were plugged at original installation, and then address the tubes found during the inspections by plugging approximately 20% of the tubes that cannot be repaired easily and repairing the remaining 80% with sleeving, which is a common and proven repair strategy," O'Brien said.

Holtec still needs permits from the NRC. "Holtec must ensure the generators will meet NRC requirements if the agency authorizes returning Palisades to operational status," an NRC spokesperson said.

The NRC saidlast month that preliminary results from inspections "identified a large number of steam generator tubes with indications that require further analysis and/or repair."

Steam generator issues can pose problems for nuclear power plants. Parts of the San Onofre Nuclear Generating Station in California were shut in 2012 after steam generators that had a design flaw leaked. Problems with new generators led to the closure of the plant in 2013.



Reporting by Timothy Gardner; Editing by Andrea Ricci and David Gregorio

</body></html>

Bildirim: XM Group şirketlerinin her biri yalnızca gerçekleştirme hizmeti ve online yatırım platformumuza erişim sağlar. Herhangi bir kişinin web sitesinde bulunan veya web sitesi üzerinden sağlanan içeriği görüntülemesine ve/veya kullanmasına izin vermek, bu hizmeti değiştirmek veya genişletmek amaçlı değildir ve bu hizmeti ne değiştirir ne de genişletir. Bu tür erişim ve kullanım her zaman şunlara tabidir: (i) Şartlar ve Koşullar; (ii) Risk Uyarıları ve (iii) Tam Bildirim. Bu nedenle bu tür içerikler yalnızca genel bilgi amacıyla sağlanır. Özellikle, online yatırım platformumuzun içeriklerinin finans piyasalarında herhangi bir işleme girmek için bir teşvik veya bir teklif olmadığını lütfen dikkate alın. Herhangi bir finans piyasasında yatırım yapmak sermayeniz için önemli düzeyde risk taşır.

Online yatırım platformumuzda yayınlanan tüm materyaller yalnızca eğitim/bilgilendirme amaçlıdır ve finansal tavsiye, yatırım vergisi veya yatırım tavsiyesi ve önerileri ya da yatırım fiyatlarımızın kaydı veya herhangi bir finansal enstrümanda işlem yapılması için bir teklif veya teşvik ya da talep edilmemiş finansal promosyonları içermez ve içerdiği şeklinde bir değerlendirme yapılmamalıdır.

Görüşler, haberler, araştırma, analizler, fiyatlar, diğer bilgiler veya bu web sitesinde bulunan üçüncü taraf sitelere verilen bağlantılar gibi her türlü üçüncü taraf içeriğin yanı sıra XM tarafından hazırlanan içerik de “olduğu gibi” esasına göre, genel piyasa yorumu olarak sağlanır ve bir yatırım tavsiyesi oluşturmaz. Herhangi bir içeriğin yatırım araştırması olarak yorumlanmasıyla ilgili olarak, içeriğin bağımsız yatırım araştırmasını desteklemek üzere tasarlanmış yasal gerekliliklere uygun hazırlanmadığını ve bu amacın güdülmediğini, aynı şekilde ilgili yasalar ve mevzuatlar kapsamında pazarlama iletişimi olarak değerlendirileceğini dikkate almalı ve kabul etmelisiniz. Buradan erişebileceğiniz Bağımsız Olmayan Yatırım Araştırması Bildirimimizi ve yukarıdaki bilgilerle ilgili Risk Uyarımızı okuduğunuzdan ve anladığınızdan emin olun.

Risk uyarısı: Sermayeniz risk altında. Kaldıraçlı ürünler herkese uygun olmayabilir. Lütfen Risk Bildirimi'mizi dikkate alın.