U.S. regulators raise questions about siting data centers at power plants



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 1-U.S. regulators raise questions about siting data centers at power plants</title></head><body>

New throughout, adds details and comments from Google and PJM market monitor

By Laila Kearney

NEW YORK, Nov 1 (Reuters) -Costs and reliability concerns related to the burgeoning trend of building energy-intensive data centers next to U.S. power plants were the focus of a technical conference held on Friday by the Federal Energy Regulatory Commission.

As the technology industry races to deploy data centers for technologieslike generative artificial intelligence, quickly accessing the massive amounts of electricity for the centers has become a critical problem.

Connecting data centers directly to power plants, in an arrangement known as co-location, has presented a fast routeto accessing large amounts of electricity, instead of toiling for years in queues to connect to the broader grid.

"I believe that the federal government, including this agency, should be doing the very best it can to nurture and foster their development," said FERC Chairman Willie Phillips, adding he consideredAI centers vitalto national security and the U.S.economy.

This year Amazon bought a data center powered directly by a Pennsylvania nuclear plant owned by Talen Energy. Shares of fellow major independent nuclear operators, including Constellation and Vistra, have shot up this year partially on the prospect of striking similar deals.

The possibility of a ballooning number of co-located data centers has raised questionsabout potentially higherpower bills for everyday customers because the centers will usegrid infrastructure and services paid for by the public.

Connecting data centers directly to power plants that had been supplying power to the public hasalso sparked reliability concerns, in part, because they can divert steadypower from the grid.

FERC questioned whether the co-located centers will use the grid as backup power and what will happen if the neighboring power plant unexpectedly goes offline.

"Does the customer get to still draw power from the grid? Because if it does, that's going to have a huge impact," said Commissioner Mark Christie.

The technical conference could lead to new co-located data center guidelines, including ones that determinewho is responsible for transmission and distribution upgrade costs and how agreements for thecenters are governed.

FERC is also currently gathering details on a regulatory battle being waged by electric utilities over the co-located Amazon data center agreement with Talen Energy. Talen's interconnection agreement for the center is being opposed by utilities Exelon and American Electric Power, and FERC's decision on the case couldset a precedent for similar deals.

The data center would take as much as 960 megawatts, or enough to power nearly 1 million American homes, of nuclear energy from the largest U.S. electrical grid.

At Friday's conference, Joseph Bowring, watchdog for PJM Interconnection market activity, said more co-located data centers at nuclear plants would exacerbate the region's supply-demand imbalance.

"It is not a way to solve the problem, it is a way to actually make it worse," Bowring said, recommending that data center developers instead help bring more power online.

Brian George, Google's head of global energy market development and policy, said Google's interest in co-located developments is being driven by a need to access electricity and not to avoid the associated costs.

"We will pay for our fair share of those costs," George said.



Reporting by Laila Kearney; Editing by David Gregorio

</body></html>

สินทรัพย์ที่เกี่ยวข้อง


ข่าวล่าสุด

Chubb announces estimated net losses for Hurricane Milton


Sherwin-Williams gains, set to join Dow Jones Industrial Average

U
D
S

North Korea vows to continue what it calls self-defense efforts, KCNA says


CIF/FOB Gulf Grain-Nearby soybean barge bids firm on good demand


Chewy rises as company set to join S&P MidCap 400

ข้อความสงวนสิทธิ์: บริษัทในเครือ XM Group มีการให้บริการดำเนินคำสั่งและการเข้าถึงแพลตฟอร์มซื้อขายออนไลน์ของเรา ซึ่งช่วยให้บุคคลสามารถดู และ/หรือใช้ข้อมูลที่มีอยู่บนหรือผ่านทางเว็บไซต์ ซึ่งไม่ได้มีการเปลี่ยนแปลงหรือขยายความจากสิ่งนี้ อีกทั้งการเข้าถึงดังกล่าวจะอยู่ภายใต้: (i) เงื่อนไขและข้อตกลง; (ii) คำเตือนเกี่ยวกับความเสี่ยง; และ (iii) ข้อความสงวนสิทธิ์ฉบับเต็ม ดังนั้นข้อมูลดังกล่าวจึงเป็นเพียงแค่ข้อมูลทั่วไปเท่านั้น นอกจากนี้โปรดทราบว่าข้อมูลต่างๆ บนแพลตฟอร์มซื้อขายออนไลน์ของเราไม่ได้มีการเชื้อเชิญหรือถือเป็นข้อเสนอให้ทำธุรกรรมใดๆ บนตลาดการเงิน และการซื้อขายบนตลาดการเงินใดๆ มีความเสี่ยงในระดับสูงกับเงินทุนของคุณ

เนื้อหาทั้งหมดที่ถูกเผยแพร่อยู่บนแพลตฟอร์มเทรดออนไลน์ของเรามีวัตถุประสงค์เพื่อให้ข้อมูล/ความรู้เท่านั้นและไม่มี – และไม่ควรถือว่ามี – คำแนะนำด้านการเงิน, ภาษีการลงทุน, หรือการเทรด หรือข้อมูลราคาย้อนหลัง, หรือข้อเสนอ, หรือการเชื้อเชิญให้ทำธุรกรรมใดๆ เกี่ยวกับตราสารทางการเงินหรือโปรโมชั่นทางการเงินสำหรับท่าน

เนื้อหาของบุคคลที่สามใดๆ รวมถึงเนื้อหาที่ถูกจัดเตรียมขึ้นโดย XM เช่น ข้อคิดเห็น, ข่าวสาร, บทวิเคราะห์, ราคา, ข้อมูลอื่นๆ หรือลิงก์ไปยังเว็บไซต์ของบุคคลที่สามที่อยู่ในเว็บไซต์นี้ถูกจัดทำขึ้น “ตามที่เป็น” ซึ่งเป็นการแสดงความคิดเห็นเกี่ยวกับตลาดโดยทั่วไปและไม่ถือเป็นคำแนะนำด้านการลงทุน เนื่องจากเนื้อหาเหล่านี้ถือเป็นบทวิจัยด้านการลงทุน ท่านจะต้องทราบและยอมรับว่า เนื้อหาเหล่านี้ไม่ได้มีวัตถุประสงค์และไม่ได้มีการถูกจัดเตรียมขึ้นตามข้อกำหนดทางด้านกฎหมายที่ถูกออกแบบขึ้นมาเพื่อส่งเสริมการวิจัยด้านการลงทุนที่เป็นอิสระ ดังนั้นเนื้อหาเหล่านี้ถือเป็นการสื่อสารทางการตลาดภายใต้กฎหมายและกฎระเบียบที่เกี่ยวข้อง โปรดอ่านและทำความเข้าใจประกาศเกี่ยวกับบทวิจัยด้านการลงทุนที่ไม่ได้มีความเป็นอิสระและคำเตือนเกี่ยวกับความเสี่ยงซึ่งมีความเกี่ยวข้องกับข้อมูลต่างๆ ดังที่ได้กล่าวไปแล้ว โดยท่านสามารถดูได้ ที่นี่

คำเตือนความเสี่ยง: เงินทุนของท่านมีความเสี่ยง ผลิตภัณฑ์ที่มีอัตราทดอาจไม่เหมาะสำหรับนักลงทุนบางราย โปรดศึกษาและทำความเข้าใจเอกสารเปิดเผยข้อมูลความเสี่ยงของเรา