Talen focused on data center demand as it considers axing crypto business



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Talen focused on data center demand as it considers axing crypto business</title></head><body>

Adds financial details and CEO quotes starting in sixth paragraph

By Laila Kearney

NEW YORK, Aug 13 (Reuters) -Talen Energy TLN.O is focused on capturing surging demand from data center developers as the independent power company looks to pivot away from its crypto mining operation, company executives said on Tuesday.

Talen is among a group of U.S. electric companies benefiting from the power needs of artificial intelligence and cloud computing data centers, with shares of Talen upnearly 100% since the start of the year.

"It's not a strategic asset for us and we are looking at... otheralternatives," Talen Energy Chief Executive Officer Mark McFarland said of the crypto mining business ona second-quarter earnings call.

Reuters reported earlier thismonth that Talen was lookingto sell its stake in a bitcoinmining center at the site of a Pennsylvania nuclear power plant

Talen raised its earnings and free cash flow forecasts for the year as it benefits from higher power use and prices, bigger payments from regional grid operator PJM Interconnection and a payout for a data center sold to Amazon.com AMZN.O early this year.

Talen revised up its adjusted EBITDA range for 2024 to $720 million to $780 million, from $600 million to $800 million previously. Its free cash flow estimate for the year was revised to $245 million to $285 million, from $160 million to $310 million previously. The company benefited from unseasonably warm weather in the three months ended on June 30, among other factors.

Talen expects to receive $670 million from capacity revenues for the 2025/2026 planning year, or $470 million more than the previous year, following a capacity auction in the PJM market.

Talen also plans on $300 million of Amazon data center campus escrow to be released in the third quarter.

The data center is at the center of a battle between Talen and regulated electric utilities, American Electric Power and Exelon, which say the build-out to connect the center could raise costs for everyday power customers.

The Federal Energy Regulatory Commission (FERC) is reviewing the amended interconnection service agreement for the center, and will hold a technical conference this fall more broadly on what are known as co-located data centers, in which data centers are located at the power plant sites that fuel them.

McFarland said he was optimistic that FERC would approve the amended agreement.



Reporting by Laila Kearney; Editing by Emelia Sithole-Matarise and Leslie Adler

</body></html>

Ansvarsfriskrivning: XM Group-enheter tillhandahåller sin tjänst enbart för exekvering och tillgången till vår onlinehandelsplattform, som innebär att en person kan se och/eller använda tillgängligt innehåll på eller via webbplatsen, påverkar eller utökar inte detta, vilket inte heller varit avsikten. Denna tillgång och användning omfattas alltid av i) villkor, ii) riskvarningar och iii) fullständig ansvarsfriskrivning. Detta innehåll tillhandahålls därför uteslutande som allmän information. Var framför allt medveten om att innehållet på vår onlinehandelsplattform varken utgör en uppmaning eller ett erbjudande om att ingå några transaktioner på de finansiella marknaderna. Handel på alla finansiella marknader involverar en betydande risk för ditt kapital.

Allt material som publiceras på denna sida är enbart avsett för utbildnings- eller informationssyften och innehåller inte – och ska inte heller anses innehålla – rådgivning och rekommendationer om finansiella frågor, investeringsskatt eller handel, dokumentation av våra handelskurser eller ett erbjudande om, eller en uppmaning till, en transaktion i finansiella instrument eller oönskade finansiella erbjudanden som är riktade till dig.

Tredjepartsinnehåll, liksom innehåll framtaget av XM såsom synpunkter, nyheter, forskningsrön, analyser, kurser, andra uppgifter eller länkar till tredjepartssajter som återfinns på denna webbplats, tillhandahålls i befintligt skick, som allmän marknadskommentar, och utgör ingen investeringsrådgivning. I den mån som något innehåll tolkas som investeringsforskning måste det noteras och accepteras att innehållet varken har varit avsett som oberoende investeringsforskning eller har utarbetats i enlighet med de rättsliga kraven för att främja ett sådant syfte, och därför är att betrakta som marknadskommunikation enligt tillämpliga lagar och föreskrifter. Se till så att du har läst och förstått vårt meddelande om icke-oberoende investeringsforskning och riskvarning om ovannämnda information, som finns här.

Riskvarning: Ditt kapital riskeras. Hävstångsprodukter passar kanske inte alla. Se vår riskinformation.