US nuclear plant unfit for quick resurrection, former lead engineer says



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>US nuclear plant unfit for quick resurrection, former lead engineer says</title></head><body>

By Timothy Gardner

WASHINGTON, Aug 2 (Reuters) -The first U.S. nuclear plant to ever try reopening after undergoing preparations for permanent closure is not fit to restart anytime soon because it sidestepped important safety work for years before retirement, a former official at the reactor said.

Power company Entergy ETR.N closed the Palisades reactor in Michigan in 2022, after the plant generated electricity for more than 50 years. Privately-held Holtec International bought Palisades shortly after and has since secured a $1.52 billion conditional U.S. loan guarantee to restart. Holtec seeks to open the plant in about a year.

The fate of Palisades is closely watched by the nuclear industry as at least two other shuttered plants, including a unit at Constellation Energy's CEG.O Three Mile Island, consider reopening.

The administration of President Joe Biden sees nuclear power as a critical tool in the fight against climate change and supports efforts to restart closed plants, delay retirements of existing ones, and speed permitting for new projects.

"I'm pro-nuclear, but they selected the wrong horse to ride to town on," said Alan Blind, who was engineering director at the Palisades plant from 2006 to 2013 under Entergy.

Blind said the plant got exemptions from the U.S. Nuclear Regulatory Commission, the nuclear safety regulator, allowing it to fall short of safety design standards that more modern plants must adhere to because it was nearing retirement.

Those safety standards include prevention of cooling systems being clogged by the breakdown of insulation on pipes, defense against earthquakes, and reduction of risks to fires, Blind said, adding he had been monitoring the plants’ exemption requests since his retirement.

"I'm worried that the NRC will not insist that the generic safety issues be the fixed before they allow Palisades to restart," Blind told Reuters.

Scott Burnell, an NRC spokesperson, said the safety review of Holtec's applications "will include examining how Holtec plans to follow through on technical issues, such as what Mr. Blind describes, that were unresolved when the plant shut down in 2022."

"Those plans will be public to the greatest extent possible," and the NRC will allow a restart only if Holtec meets safety and environmental requirements. Burnell added NRC will soon offer an opportunity to offer legal challenges to Holtec's requests to restart, a standard procedure.

Holtec believes Palisades can restart in about a year within the NRC's existing regulatory framework, said spokesperson Pat O'Brien. "As part of the repowering, Palisades will undergo extensive inspections, testing, maintenance, system and equipment upgrades and modifications to ensure the continuation of safe and reliable operation throughout the plant’s extended operational life," O'Brien said.

Entergy supports the effort to re-open Palisades, said spokesperson Mark Sullivan. He did comment on Blind's concerns about safety standards at the plant.

Entergy shut Palisades in May 2022, two weeks ahead of schedule over a glitch with a control rod, despite a $6 billion federal program to save nuclear plants suffering from rising costs and competition from natural gas and renewable energy.

The Biden administration's Loan Programs Office at the Department of Energy issued Holtec a conditional $1.52 billion loan guarantee in March to restart Palisades.

The LPO referred questions to the NRC.



Reporting by Timothy Gardner, Editing by Nick Zieminski

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.