US nuclear missile program to be years behind schedule, over budget, Pentagon says
WASHINGTON, July 8 (Reuters) -A Pentagon program to replace some of its aging intercontinental ballistic missiles will be years behind schedule and 81% over budget, the U.S. military said on Monday.
The project, now named the Sentinel intercontinental ballistic missile program, is designed and managed by Northrop Grumman NOC.N, and aims to replace aging Minuteman III missiles.
The program is estimated to cost $140.9 billion, up 81% from a cost estimate in September 2020.
"We are fully aware of the costs, but we are also aware of the risks of not modernizing our nuclear forces and not addressing the very real threats we confront," U.S. Under Secretary of Defense for Acquisition and Sustainment William LaPlante told reporters. LaPlante certified that the program should continue despite the cost overrun.
"There are reasons for the cost growth, but there are no excuses. We are already working to address the root causes, and more importantly, we believe we are on the right path to defend our nation," LaPlante added.
The majority of the cost growth is associated with launch facilities, launch centers and other processes involved with converting from Minuteman III to Sentinel. Reuters has reported that the "unmodified program" cost could be as much as $160 billion.
The new Sentinel cost estimate eclipses an increase to "at least" $131 billion that the Air Force made public in January.
That triggered the Nunn-McCurdy Act, a 1982 law that requires the Pentagon to formally justify to Congress the importance of a program whose unit acquisition costs have risen more than 25% above a baseline.
Reporting by Idrees Ali and Phil Stewart; Editing by Bill Berkrot
Latest News
Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.
All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.
Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.