Talen focused on data center demand as it considers axing crypto business



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Talen focused on data center demand as it considers axing crypto business</title></head><body>

Adds financial details and CEO quotes starting in sixth paragraph

By Laila Kearney

NEW YORK, Aug 13 (Reuters) -Talen Energy TLN.O is focused on capturing surging demand from data center developers as the independent power company looks to pivot away from its crypto mining operation, company executives said on Tuesday.

Talen is among a group of U.S. electric companies benefiting from the power needs of artificial intelligence and cloud computing data centers, with shares of Talen upnearly 100% since the start of the year.

"It's not a strategic asset for us and we are looking at... otheralternatives," Talen Energy Chief Executive Officer Mark McFarland said of the crypto mining business ona second-quarter earnings call.

Reuters reported earlier thismonth that Talen was lookingto sell its stake in a bitcoinmining center at the site of a Pennsylvania nuclear power plant

Talen raised its earnings and free cash flow forecasts for the year as it benefits from higher power use and prices, bigger payments from regional grid operator PJM Interconnection and a payout for a data center sold to Amazon.com AMZN.O early this year.

Talen revised up its adjusted EBITDA range for 2024 to $720 million to $780 million, from $600 million to $800 million previously. Its free cash flow estimate for the year was revised to $245 million to $285 million, from $160 million to $310 million previously. The company benefited from unseasonably warm weather in the three months ended on June 30, among other factors.

Talen expects to receive $670 million from capacity revenues for the 2025/2026 planning year, or $470 million more than the previous year, following a capacity auction in the PJM market.

Talen also plans on $300 million of Amazon data center campus escrow to be released in the third quarter.

The data center is at the center of a battle between Talen and regulated electric utilities, American Electric Power and Exelon, which say the build-out to connect the center could raise costs for everyday power customers.

The Federal Energy Regulatory Commission (FERC) is reviewing the amended interconnection service agreement for the center, and will hold a technical conference this fall more broadly on what are known as co-located data centers, in which data centers are located at the power plant sites that fuel them.

McFarland said he was optimistic that FERC would approve the amended agreement.



Reporting by Laila Kearney; Editing by Emelia Sithole-Matarise and Leslie Adler

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.