Golden Pass LNG construction could return to normal speed after settlement



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>Golden Pass LNG construction could return to normal speed after settlement</title></head><body>

By Curtis Williams

HOUSTON, July 22 (Reuters) -Work to complete the QatarEnergy QATPE.UL and Exxon Mobil XOM.N $11 billion liquefied natural gas project in Texas could speed up following a settlement agreement allowing the joint venture to choose a new contractor to take over the development, according to court documents.

The project's original main contractor, Zachry HoldingsZHII.UL, filed for Chapter 11 bankruptcy protection in March, saying the Golden Pass project - known as GPX - was at least $2.4 billion over the original budget.

A settlement with Zachry for the company to step aside is expected to put an end to the standoff that delayed the project. First LNG output from the 15 million metric ton per annum (MTPA) project is now expected in 2025, rather than the end of this year as originally planned.

The project, at the Sabine Pass site of a former gas-import terminal that was converted to process natural gas for LNG exports, is one of two large U.S. LNG facilities whose startups were expected to significantly expand supplies from the world's top exporter of the superchilled fuel in the next 12 months.

Zachry on Friday filed an emergency motion with the U.S. bankruptcy court for the Southern District of Texas in Houston asking it to approve a settlement with Golden Pass LNG and Chiyoda International Corp, expected to lead to Zachary emerging from bankruptcy.

The agreement will allow Chiyoda to take over the project as the lead contractor for engineering, procurement and construction, and for paying vendors.

"The settlement will facilitate the completion of the GPX Project and create a path for the debtors (Zachry) to emerge from bankruptcy," the court document said.

The parties have managed to keep lines of communication open, progressing toward a consensual resolution of the issues, Zachry said in its filing.

Zachry said it would not comment until after the settlement approval hearing, scheduled for Wednesday.

The proposed deal is expected to allow direct payment of vendors' approved claims by Golden Pass, subject to a cap, with Zachry agreeing to pay the balance of any such allowed claims.

It also allows for the immediate transition of work from Zachry to joint venture partners, allowing them to rehire workers, advance scope, and complete the project, the court document showed.





Reporting by Curtis Williams in Houston; Editing by Bill Berkrot

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.