NEW YORK, Nov 4 (Reuters) -Constellation Energy will continue to pursue deals to develop data centers on the sites of its U.S. power plants, days after federal regulators dealt a blow to the so-called co-located arrangements, company executives said on Monday.
The Federal Energy Regulatory Commission on Friday rejected an agreement to increase the power capacity of an Amazon data center connected directly to Talen Energy's TLN.O nuclear power plant in Pennsylvania in a decision seen as chilling similar deals.
Constellation said it is seeking guidance from regulators after FERC's decision about co-location, which had become a promising prospect for Big Tech's plans to quickly access large amounts of power for its AI expansion instead of waiting for years to connect to the grid.
"We will pursue this regular clarity while simultaneously pursuing commercial strategies for co-location that are permitted under our existing rules," Constellation CEO Joseph Dominguez said on a company earnings call.
Dominguez outlined what future co-located agreements would look like, including that nuclear energy directly fueling data centers be required to switch over to powering the grid in times of supply emergencies and that backup power for the centers could be sold back to the regional market.
"There are multiple regulatory and commercial pathways to resolve the co-location issues, and we will work quickly with customers and other stakeholders to put these in place."
Constellation CEG.O, which is the largest operator of U.S. nuclear power plants, had backed Talen in the regulatory battle. Shares of the nuclear power operators had shot up this year partly on the prospect of developing co-located data centers.
Constellation stock was down about 10% on Monday.
The FERC fight was brought by electric utilities Exelon and American Electric Power, which opposed the Talen-Amazon data center interconnection agreement, saying that it threatened to raise power bills for everyday customers and erode grid reliability.
Talen's Susquehanna nuclear-powered data center campus, sold to Amazon this year, would have the capacity of 960 megawatts, or enough electricity for all of the homes in Philadelphia.
In a 2-1 vote, FERC shot down Talen's request to expand the capacity of data center beyond 300 megawatts. The vote followed a FERC technical conference to discuss broader concerns about co-locating data centers.
Diverting that electricity, which currently flows from the nuclear plant to the broader grid, could unfairly shift costs to the public and worsen a supply-demand imbalance in the PJM Interconnection regional power market, the majority of voting commissioners said.
Talen Energy, in a statement posted to its website on Sunday, said it would consider various methods to quickly power up data centers.
"The data center economy will require an all-of-the-above approach to satisfy the increased demand, including co-location," the company said.
Reporting by Laila Kearney; Editing by Aurora Ellis
Ativos relacionados
Últimas notícias
Isenção de Responsabilidade: As entidades do XM Group proporcionam serviço de apenas-execução e acesso à nossa plataforma online de negociação, permitindo a visualização e/ou uso do conteúdo disponível no website ou através deste, o que não se destina a alterar ou a expandir o supracitado. Tal acesso e uso estão sempre sujeitos a: (i) Termos e Condições; (ii) Avisos de Risco; e (iii) Termos de Responsabilidade. Este, é desta forma, fornecido como informação generalizada. Particularmente, por favor esteja ciente que os conteúdos da nossa plataforma online de negociação não constituem solicitação ou oferta para iniciar qualquer transação nos mercados financeiros. Negociar em qualquer mercado financeiro envolve um nível de risco significativo de perda do capital.
Todo o material publicado na nossa plataforma de negociação online tem apenas objetivos educacionais/informativos e não contém — e não deve ser considerado conter — conselhos e recomendações financeiras, de negociação ou fiscalidade de investimentos, registo de preços de negociação, oferta e solicitação de transação em qualquer instrumento financeiro ou promoção financeira não solicitada direcionadas a si.
Qual conteúdo obtido por uma terceira parte, assim como o conteúdo preparado pela XM, tais como, opiniões, pesquisa, análises, preços, outra informação ou links para websites de terceiras partes contidos neste website são prestados "no estado em que se encontram", como um comentário de mercado generalizado e não constitui conselho de investimento. Na medida em que qualquer conteúdo é construído como pesquisa de investimento, deve considerar e aceitar que este não tem como objetivo e nem foi preparado de acordo com os requisitos legais concebidos para promover a independência da pesquisa de investimento, desta forma, deve ser considerado material de marketing sob as leis e regulações relevantes. Por favor, certifique-se que leu e compreendeu a nossa Notificação sobre Pesquisa de Investimento não-independente e o Aviso de Risco, relativos à informação supracitada, os quais podem ser acedidos aqui.