Environmentalists sue over US approval of ioneer's Nevada lithium mine
Adds responses from Interior Department and company, paragraphs 5-7
Lawsuit claims mine threatens rare wildflower and environment
Interior Department and ioneer defend mine approval
Mine to supply Ford and other EV makers, backed by $700 million loan
By Nate Raymond, Ernest Scheyder
Oct 31 (Reuters) -Environmental and Indigenous groups on Thursday filed a lawsuit challenging the U.S. Interior Department's approval of ioneer's INR.AX Rhyolite Ridge lithium mine in Nevada, the first domestic source of the battery metal to be permitted by Democratic President Joe Biden's administration.
In a lawsuit filed in federal court in Las Vegas, groups including the Center for Biological Diversity argued the project posed an existential risk to the rare wildflower Tiehm’s buckwheat and could drive it to extinction.
They said the mine would also adversely impact groundwater, springs, wetlands, air quality, cultural resources and wildlife habitats, and would transform a remote part of rural Nevada into an industrial complex.
The groups said the Interior Department's Bureau of Land Management (BLM) approved the mine without ensuring that it would not jeopardize the wildflower or unduly impact the environment in violation of the National Environmental Policy Act, the Federal Lands Policy and Management Act, and the Endangered Species Act.
The Interior Department declined to comment.
Australia-based ioneer said it does not expect the lawsuit to "meaningfully affect our proposed development timeline" and that it believes the project can be developed sustainably.
"We are confident that the BLM will prevail against this lawsuit," said Chad Yeftich, ioneer's vice president of corporate development and external affairs. "We intend to intervene and vigorously defend the BLM's decision, which was based on its careful and thorough permitting process."
The critical minerals miner received approval for the mine last week following a more-than six-year review process during which regulators, ioneer and conservationists tussled over the fate of Tiehm’s buckwheat.
The permit cleared the way for development of a mine that will become a key supplier to Ford Motor F.N and other electric-vehicle manufacturers. It was issued amid a flurry of recent moves by Biden administration officials to support critical minerals production and offset China's market dominance.
The permit also unlocked a $700 million loan from the U.S. Department of Energy, as well as a $490 million equity investment from Sibanye Stillwater SSWJ.J to fund the project.
The Interior Department said when it approved the mine that it had taken numerous steps to protect the ecosystem near the mine site, roughly 225 miles (362 km) north of Las Vegas.
The project contains enough lithium to power roughly 370,000 EVs each year. Construction is slated to begin next year, with production commencing by 2028.
Reporting by Nate Raymond in Boston and Ernest Scheyder in Houston
Editing by Matthew Lewis
Laatste nieuws
Disclaimer: De entiteiten van de XM Group bieden diensten en toegang tot ons online handelsplatform op basis van uitsluitend-uitvoering, waardoor een persoon de beschikbare content op of via de website kan bekijken en/of gebruiken, zonder dat dit is bedoeld voor wijziging of uitbreiding. Dergelijk(e) toegang en gebruik vallen onder: (i) de algemene voorwaarden; (ii) risicowaarschuwingen; en de (iii) volledige disclaimer. Dergelijke content wordt daarom alleen aangeboden als algemene informatie. Wees u er daarnaast vooral van bewust dat de inhoud op ons online handelsplatform geen verzoek of aanbieding omvat om transacties op de financiële markten uit te voeren. Het beleggen op welke financiële markt dan ook vormt een aanzienlijk risico voor uw vermogen.
Alle materialen die op ons online handelsplatform worden gepubliceerd zijn bedoeld voor educatieve/informatieve doeleinden en omvatten geen – en moeten niet worden beschouwd als het bevatten van – financieel, vermogensbelastings- of handelsadvies en aanbevelingen, of een overzicht van onze handelsprijzen, of een aanbod of aanvraag van een transactie in financiële instrumenten of ongevraagde financiële promoties voor u.
Alle content van derden, alsmede content die is voorbereid door XM, zoals opinies, nieuws, onderzoeken, analyses, prijzen en andere informatie of koppelingen naar externe websites op deze website worden aangeboden op een 'zoals-ze-zijn'-basis, als algemene marktcommentaren, en vormen geen beleggingsadvies. Voor zover dat content wordt beschouwd als beleggingsonderzoek, moet u zich ervan bewust zijn en accepteren dat de content niet bedoeld was en niet is voorbereid in overeenstemming met de wettelijke vereisten die zijn opgesteld om de onafhankelijkheid van beleggingsonderzoek te bevorderen en als zodanig onder de geldende wetgeving en richtlijnen moet worden beschouwd als marketingcommunicatie. Zorg ervoor dat u onze Mededeling over niet-onafhankelijk beleggingsonderzoek en risicowaarschuwing in verband met de voorgaande informatie doorneemt en begrijpt; die kunt u hier lezen.