Orsted flags delay to US offshore wind project, new impairment losses



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 3-Orsted books new impairment losses, flags delay at US offshore wind project</title></head><body>

Q2 EBITDA up 59%, beats expectations

Books impairments of U.S. project delay

Keeps full-year profit forecast, says will lower investments

Shares down nearly 8%

Adds share price in paragraphs 1 and 4, context and background in paragraphs 5-6

By Jacob Gronholt-Pedersen

COPENHAGEN, Aug 15 (Reuters) -Renewable energy group Orsted ORSTED.CO booked 3.2 billion Danish crowns ($472 million) in impairment losses in the second quarter, due partly to a delay in construction of a major U.S. offshore wind project, sending its shares down almost 8% on Thursday.

The world's biggest offshore wind developer pushed back the start of commercial operations at its 704 megawatt (MW) Revolution Wind project off Rhode Island and Connecticut to 2026 from 2025, it said in its quarterly results statement.

The impairment losses booked also related to its Ocean Wind project in the United States whose development it halted last year, an increase in U.S. long-dated interest rates, and its decision to cease development of a green e-methanol project which was due to open in Sweden next year.

Shares in Orsted, once a green investor favourite, were trading 7.6% down at 0710 GMT on Thursday. They remain at less than one-third of their value since peaking in early 2021.

The company last year found itself at the centre of a perfect storm of rising inflation, higher interest rates and supply chain delays, forcing it to cancel offshore projects in the United States and related impairments surged above $4 billion.

In February, it trimmed its investment and capacity targets and paused dividend payouts following a strategic review of its business.

Still, the company beat analyst expectations with a 59% rise in second-quarter profit before interest, tax, depreciation and amortisation (EBITDA) and excluding new partnerships of 5.27 billion Danish crowns.

That topped an average forecast of 4.41 billion crowns in a poll of analysts provided by Orsted.

"Despite encouraging progress on our U.S. offshore wind project Revolution Wind, the construction of the onshore substation for the project has been delayed," CEO Mads Nipper said in a statement.

Impairment losses related to the project alone amounted to 2.1 billion crowns, Orsted said.

"This is, of course, unsatisfactory, and we continue our dedicated efforts to de-risk our portfolio," he said.

Orsted kept its full-year profit forecast unchanged but said it would lower investments this year.

"Orsted's operations are performing well, and particularly the earnings from our offshore wind farms, and thus our core business, have increased," said Nipper.


($1 = 6.7745 Danish crowns)



Reporting by Jacob Gronholt-Pedersen; editing by Terje Solsvik and Emelia Sithole-Matarise

</body></html>

면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.

온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.

이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.

리스크 경고: 고객님의 자본이 위험에 노출 될 수 있습니다. 레버리지 상품은 모든 분들에게 적합하지 않을수 있습니다. 당사의 리스크 공시를 참고하시기 바랍니다.