Talen focused on data center demand as it considers axing crypto business



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Talen focused on data center demand as it considers axing crypto business</title></head><body>

Adds financial details and CEO quotes starting in sixth paragraph

By Laila Kearney

NEW YORK, Aug 13 (Reuters) -Talen Energy TLN.O is focused on capturing surging demand from data center developers as the independent power company looks to pivot away from its crypto mining operation, company executives said on Tuesday.

Talen is among a group of U.S. electric companies benefiting from the power needs of artificial intelligence and cloud computing data centers, with shares of Talen upnearly 100% since the start of the year.

"It's not a strategic asset for us and we are looking at... otheralternatives," Talen Energy Chief Executive Officer Mark McFarland said of the crypto mining business ona second-quarter earnings call.

Reuters reported earlier thismonth that Talen was lookingto sell its stake in a bitcoinmining center at the site of a Pennsylvania nuclear power plant

Talen raised its earnings and free cash flow forecasts for the year as it benefits from higher power use and prices, bigger payments from regional grid operator PJM Interconnection and a payout for a data center sold to Amazon.com AMZN.O early this year.

Talen revised up its adjusted EBITDA range for 2024 to $720 million to $780 million, from $600 million to $800 million previously. Its free cash flow estimate for the year was revised to $245 million to $285 million, from $160 million to $310 million previously. The company benefited from unseasonably warm weather in the three months ended on June 30, among other factors.

Talen expects to receive $670 million from capacity revenues for the 2025/2026 planning year, or $470 million more than the previous year, following a capacity auction in the PJM market.

Talen also plans on $300 million of Amazon data center campus escrow to be released in the third quarter.

The data center is at the center of a battle between Talen and regulated electric utilities, American Electric Power and Exelon, which say the build-out to connect the center could raise costs for everyday power customers.

The Federal Energy Regulatory Commission (FERC) is reviewing the amended interconnection service agreement for the center, and will hold a technical conference this fall more broadly on what are known as co-located data centers, in which data centers are located at the power plant sites that fuel them.

McFarland said he was optimistic that FERC would approve the amended agreement.



Reporting by Laila Kearney; Editing by Emelia Sithole-Matarise and Leslie Adler

</body></html>

면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.

온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.

이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.

리스크 경고: 고객님의 자본이 위험에 노출 될 수 있습니다. 레버리지 상품은 모든 분들에게 적합하지 않을수 있습니다. 당사의 리스크 공시를 참고하시기 바랍니다.