Golden Pass LNG asks US regulator for 3-year extension to complete construction



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Golden Pass LNG asks US regulator for 3-year extension to complete construction</title></head><body>

Adds Golden Pass comment on startup timing in paragraph 4

HOUSTON, Aug 29 (Reuters) -The developer of a Texas liquefied natural gas export project on Wednesday asked U.S. regulators for a three-year extension to complete construction ofthe $10 billion Golden Pass LNG project, citing scheduling uncertainties.

Golden Pass LNG, a joint venture of QatarEnergy QATPE.UL and Exxon Mobil XOM.N building an 18 million metric ton per annual LNG export project on the Texas coast, wrote that a change in primary contractors requires an extension until November, 2029.

Exxon and QatarEnergy this month said the project startup would be delayed until late next year. The current approval expires in November 2026 and the request signals a later startup.

The company's "goal is to produce first LNG around the end of 2025 with commercial operations following thereafter," a Golden Pass LNG spokesperson said. "The extensions we have requested build in time for contingencies."

QatarEnergy owns 70% of the joint venture and Exxon the remainder.

"The additional time will allow for the rehiring and remobilization of over 4,000 skilled workers and provide for potential uncertainties such as severe weather or hurricane delays when it may not be safe to have crews on site," Golden Pass LNG wrote the Federal Energy Regulatory Commission.

In May, Zachry Industrial, which was the primary contractor for the project, filed for bankruptcy after a dispute over $2.4 billion in cost overruns. Golden Pass LNG subsequently named CB&I, a unit of McDermott International MCDIF.PK, as lead contractor.

Golden Pass LNG is seeking the additional three-year period under a FERC provision that allows an extension if a company can show it made good faith efforts to complete a project on time, it said in a letter to FERC.

Construction of the first gas-processing unit is approximately 83% complete, and the second and third processing units are 46% and 31% complete, respectively, the FERC filing said.



Reporting by Gary McWilliams
Editing by Marguerita Choy

</body></html>

면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.

온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.

이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.

리스크 경고: 고객님의 자본이 위험에 노출 될 수 있습니다. 레버리지 상품은 모든 분들에게 적합하지 않을수 있습니다. 당사의 리스크 공시를 참고하시기 바랍니다.