Ghana anxious lithium price slump will derail maiden project



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>Ghana anxious lithium price slump will derail maiden project</title></head><body>

Atlantic Lithium says awaiting parliament's ratification

Minerals commission head fears project could be halted

Sluggish demand and lithium price slump hit projects

By Maxwell Akalaare Adombila

ACCRA, Sept 13 (Reuters) -Ghana is concerned that a slump in global lithium prices could halt its first mining project in the south central town of Ewoyaa, the head of the country's mining sector regulator told Reuters.

In October 2023, Ghana, a West African gold and cocoa producer, granted a 15-year lease to Australia-based miner Atlantic Lithium A11.AX to establish the nation's first lithium mine by the fourth quarter of 2024.

The company received environmental approval for the project on Thursday, but says a delay in parliamentary ratification of the lease was hampering its ability to meet the construction timeline and secure higher prices.

Martin Ayisi, head of Ghana's Minerals Commission, said the Ewoyaa Project that envisaged annual lithium production of around 360,000 tons risked being halted.

"It will cost Atlantic lithium around $650 to produce a ton of lithium concentrate and with the price just above $700, it's worrying for us," he said, adding that if the downturn continues, the project may get delayed further like other lithium projects globally.

The price of lithium, used in batteries for electric vehicles, has collapsed over the last two years as new supply coincided with weaker-than-expected demand for electric vehicles.

As more alternatives to lithium in the EV and battery sectors emerge, Ayisi said time was of essence for the project to pay off.

"It's not just a race against the price; it's a race to mine at a time lithium is commercially needed."

Ahmed-Salim Adam, Atlantic Lithium's general manager, told Reuters that the mine's construction, initially planned to start in July has been delayed to first quarter of 2025 because of lack of parliamentary ratification.

The ratification was delayed as lawmakers sought broader consultation, aiming to avoid repeating mistakes made during approvals of new gold mining projects.

Adam said the company would also need an operation permit from the sector regulator before it can start construction, which could take about 22 months to complete.

"It's critical that we get ratification quickly else our investors' patience is waning, especially when there are more endowed jurisdictions in the so-called lithium triangle and Mali next door," said Adam.



Reporting by Maxwell Akalaare Adombila
Additional reporting by Christian Akorlie
Editing by Bate Felix and Tomasz Janowski

</body></html>

면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.

온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.

이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.

리스크 경고: 고객님의 자본이 위험에 노출 될 수 있습니다. 레버리지 상품은 모든 분들에게 적합하지 않을수 있습니다. 당사의 리스크 공시를 참고하시기 바랍니다.