Equinor, Aker BP, Vaar face rising project costs, Norway budget shows



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Equinor, Aker BP, Vaar face rising project costs, Norway budget shows</title></head><body>

Adds Equinor, Aker BP comments in paragraphs 4-5,

By Nerijus Adomaitis

OSLO, Oct 7 (Reuters) -Energy firms Equinor EQNR.OL, Aker BP AKRBP.OL and Vaar Energi VAR.OL have raised their crown-denominate cost estimates for major oil and gas development projects offshore Norway, the country's government said on Monday.

Equinor's Johan Castberg project is now expected to cost 86 billion crowns ($8.08 billion), up from a nominal estimate of 80.3 billion seen one year ago, the government's fiscal budget documents showed.

The oilfield the Arctic Barents Sea is expected to start production by the end of this year, the company has said, two years behind its original schedule.

The field was initially estimated to cost 49 billion crowns to develop, when it was approved in 2018.

Since then, costs have increased by 25.7 billion crowns and by 2.2 billion crowns from a year ago, measured in 2024 crowns, Equinor said in a statement.

The increase from a year ago was due to Castberg's production vessel having to spend more time at a shipyard in Norway, currency effects and a general cost increase, the company said.

Meanwhile, Aker BP's Yggdrasil is expected to cost 134.4 billion crowns, up from nominal 120.2 billion seen a year go, while Vaar's Balder Future will cost 52.2 billion crowns, up from 44.5 billion crowns.

Cost increase measured in 2024 crowns were due to a weaker exchange rate, which contributed to imported inflation, said an Aker BP spokesman, adding that costs measured in U.S. dollars were within previous guidance.

Vaar Energi was not immediately available for comment.

The independent subsidiary of Italy's Eni ENI.MI warned in August that Balder's project costs would increase by pre-tax 4.3 billion crowns due to its startup being delayed until the second quarter of 2025 from end of this year.

Balder's costs have more than doubled from an initial estimate of 19.6 billion crowns in 2019.

Aker BP's Yggdrasil, Norway's largest oil and gas development since the startup of Equinor's Johan Sverdrup oilfield in 2019, is facing legal challenges, with environmental organisations disputing its approval by the energy ministry.

The company, however, has said the project, approved at the end of 2022, is on track to start production in 2027.


($1 = 10.6472 Norwegian crowns)



Reporting by Nerijus Adomaitis, editing by Terje Solsvik and David Evans

</body></html>

면책조항: XM Group 회사는 체결 전용 서비스와 온라인 거래 플랫폼에 대한 접근을 제공하여, 개인이 웹사이트에서 또는 웹사이트를 통해 이용 가능한 콘텐츠를 보거나 사용할 수 있도록 허용합니다. 이에 대해 변경하거나 확장할 의도는 없습니다. 이러한 접근 및 사용에는 다음 사항이 항상 적용됩니다: (i) 이용 약관, (ii) 위험 경고, (iii) 완전 면책조항. 따라서, 이러한 콘텐츠는 일반적인 정보에 불과합니다. 특히, 온라인 거래 플랫폼의 콘텐츠는 금융 시장에서의 거래에 대한 권유나 제안이 아닙니다. 금융 시장에서의 거래는 자본에 상당한 위험을 수반합니다.

온라인 거래 플랫폼에 공개된 모든 자료는 교육/정보 목적으로만 제공되며, 금융, 투자세 또는 거래 조언 및 권고, 거래 가격 기록, 금융 상품 또는 원치 않는 금융 프로모션의 거래 제안 또는 권유를 포함하지 않으며, 포함해서도 안됩니다.

이 웹사이트에 포함된 모든 의견, 뉴스, 리서치, 분석, 가격, 기타 정보 또는 제3자 사이트에 대한 링크와 같이 XM이 준비하는 콘텐츠 뿐만 아니라, 제3자 콘텐츠는 일반 시장 논평으로서 "현재" 기준으로 제공되며, 투자 조언으로 여겨지지 않습니다. 모든 콘텐츠가 투자 리서치로 해석되는 경우, 투자 리서치의 독립성을 촉진하기 위해 고안된 법적 요건에 따라 콘텐츠가 의도되지 않았으며, 준비되지 않았다는 점을 인지하고 동의해야 합니다. 따라서, 관련 법률 및 규정에 따른 마케팅 커뮤니케이션이라고 간주됩니다. 여기에서 접근할 수 있는 앞서 언급한 정보에 대한 비독립 투자 리서치 및 위험 경고 알림을 읽고, 이해하시기 바랍니다.

리스크 경고: 고객님의 자본이 위험에 노출 될 수 있습니다. 레버리지 상품은 모든 분들에게 적합하지 않을수 있습니다. 당사의 리스크 공시를 참고하시기 바랍니다.