Corrosion exceeds estimates at Michigan nuclear plant US wants to restart, regulator says



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Corrosion exceeds estimates at Michigan nuclear plant US wants to restart, regulator says</title></head><body>

Adds Holtec comment

By Timothy Gardner

WASHINGTON, Oct 2 (Reuters) -Holtec, the company wanting to reopen the Palisades nuclear reactor in Michigan, found corrosion cracking in steam generators "far exceeded" estimates, the U.S. nuclear power regulator said in a document published on Wednesday.

President Joe Biden's administrationthis week finalized a $1.52 billion conditional loan guarantee to the Palisades plant. It is part of an effort to support nuclear energy, which generates virtually emissions-free power, to curb climate change and to help satisfy rising electricity demand from artificial intelligence, electric vehicles and digital currency.

Palisades, which shut under a different owner in 2022, is seeking to be the first modern U.S. nuclear power plant to reopen after being fully shut.

A summary of an early September call between the U.S. Nuclear Regulatory Commission and Holtec published on Wednesday said indications of stress corrosion cracking in tubes in both of Palisade's steam generators "far exceeded estimates based on previous operating history." It found 1,163 steam generator tubes had indications of the stress cracking. There are more than 16,000 tubes in the units.

Steam generators are sensitive components that require meticulous maintenance and are among the most expensive units at a nuclear power station.

Holtec wants to return the plant to operationlate next year. Patrick O'Brien, a company spokesperson, said the results of the inspections "were not entirely unpredicted" as the standard system "layup process", or procedure for maintaining the units, was not followed when the plant went into shutdown.

But he said the return of Palisades is still on schedule and that Holtec wants to fix, and not replace, the steam generators, which he said would last for 30 years after repairs.

"We expect the repair strategy will be to 'unplug' approximately 300 tubes per steam generator that were plugged at original installation, and then address the tubes found during the inspections by plugging approximately 20% of the tubes that cannot be repaired easily and repairing the remaining 80% with sleeving, which is a common and proven repair strategy," O'Brien said.

Holtec still needs permits from the NRC. "Holtec must ensure the generators will meet NRC requirements if the agency authorizes returning Palisades to operational status," an NRC spokesperson said.

The NRC saidlast month that preliminary results from inspections "identified a large number of steam generator tubes with indications that require further analysis and/or repair."

Steam generator issues can pose problems for nuclear power plants. Parts of the San Onofre Nuclear Generating Station in California were shut in 2012 after steam generators that had a design flaw leaked. Problems with new generators led to the closure of the plant in 2013.



Reporting by Timothy Gardner; Editing by Andrea Ricci and David Gregorio

</body></html>

Avertissement : Les entités de XM Group proposent à notre plateforme de trading en ligne un service d'exécution uniquement, autorisant une personne à consulter et/ou à utiliser le contenu disponible sur ou via le site internet, qui n'a pas pour but de modifier ou d'élargir cette situation. De tels accès et utilisation sont toujours soumis aux : (i) Conditions générales ; (ii) Avertissements sur les risques et (iii) Avertissement complet. Un tel contenu n'est par conséquent fourni que pour information générale. En particulier, sachez que les contenus de notre plateforme de trading en ligne ne sont ni une sollicitation ni une offre de participation à toute transaction sur les marchés financiers. Le trading sur les marchés financiers implique un niveau significatif de risques pour votre capital.

Tout le matériel publié dans notre Centre de trading en ligne est destiné à des fins de formation / d'information uniquement et ne contient pas – et ne doit pas être considéré comme contenant – des conseils et recommandations en matière de finance, de fiscalité des investissements ou de trading, ou un enregistrement de nos prix de trading ou une offre, une sollicitation, une transaction à propos de tout instrument financier ou bien des promotions financières non sollicitées à votre égard.

Tout contenu tiers, de même que le contenu préparé par XM, tels que les opinions, actualités, études, analyses, prix, autres informations ou liens vers des sites tiers contenus sur ce site internet sont fournis "tels quels", comme commentaires généraux sur le marché et ne constituent pas des conseils en investissement. Dans la mesure où tout contenu est considéré comme de la recherche en investissement, vous devez noter et accepter que le contenu n'a pas été conçu ni préparé conformément aux exigences légales visant à promouvoir l'indépendance de la recherche en investissement et, en tant que tel, il serait considéré comme une communication marketing selon les lois et réglementations applicables. Veuillez vous assurer que vous avez lu et compris notre Avis sur la recherche en investissement non indépendante et notre avertissement sur les risques concernant les informations susdites, qui peuvent consultés ici.

Avertissement sur les risques : votre capital est à risque. Les produits à effet de levier ne sont pas recommandés pour tous. Veuillez consulter notre Divulgation des risques