Atlantic Lithium says awaiting parliament's ratification

Minerals commission head fears project could be halted

Sluggish demand and lithium price slump hit projects

By Maxwell Akalaare Adombila

ACCRA, Sept 13 (Reuters) -Ghana is concerned that a slump in global lithium prices could halt its first mining project in the south central town of Ewoyaa, the head of the country's mining sector regulator told Reuters.

In October 2023, Ghana, a West African gold and cocoa producer, granted a 15-year lease to Australia-based miner Atlantic Lithium A11.AX to establish the nation's first lithium mine by the fourth quarter of 2024.

The company received environmental approval for the project on Thursday, but says a delay in parliamentary ratification of the lease was hampering its ability to meet the construction timeline and secure higher prices.

Martin Ayisi, head of Ghana's Minerals Commission, said the Ewoyaa Project that envisaged annual lithium production of around 360,000 tons risked being halted.

"It will cost Atlantic lithium around $650 to produce a ton of lithium concentrate and with the price just above $700, it's worrying for us," he said, adding that if the downturn continues, the project may get delayed further like other lithium projects globally.

The price of lithium, used in batteries for electric vehicles, has collapsed over the last two years as new supply coincided with weaker-than-expected demand for electric vehicles.

As more alternatives to lithium in the EV and battery sectors emerge, Ayisi said time was of essence for the project to pay off.

"It's not just a race against the price; it's a race to mine at a time lithium is commercially needed."

Ahmed-Salim Adam, Atlantic Lithium's general manager, told Reuters that the mine's construction, initially planned to start in July has been delayed to first quarter of 2025 because of lack of parliamentary ratification.

The ratification was delayed as lawmakers sought broader consultation, aiming to avoid repeating mistakes made during approvals of new gold mining projects.

Adam said the company would also need an operation permit from the sector regulator before it can start construction, which could take about 22 months to complete.

"It's critical that we get ratification quickly else our investors' patience is waning, especially when there are more endowed jurisdictions in the so-called lithium triangle and Mali next door," said Adam.



Reporting by Maxwell Akalaare Adombila
Additional reporting by Christian Akorlie
Editing by Bate Felix and Tomasz Janowski

</body></html>

Descargo de responsabilidades: Cada una de las entidades de XM Group proporciona un servicio de solo ejecución y acceso a nuestra plataforma de trading online, permitiendo a una persona ver o usar el contenido disponible en o a través del sitio web, sin intención de cambiarlo ni ampliarlo. Dicho acceso y uso están sujetos en todo momento a: (i) Términos y Condiciones; (ii) Advertencias de riesgo; y (iii) Descargo completo de responsabilidades. Por lo tanto, dicho contenido se proporciona exclusivamente como información general. En particular, por favor tenga en cuenta que, los contenidos de nuestra plataforma de trading online no son ni solicitud ni una oferta para entrar a realizar transacciones en los mercados financieros. Operar en cualquier mercado financiero implica un nivel de riesgo significativo para su capital.

Todo el material publicado en nuestra plataforma de trading online tiene únicamente fines educativos/informativos y no contiene –y no debe considerarse que contenga– asesoramiento ni recomendaciones financieras, tributarias o de inversión, ni un registro de nuestros precios de trading, ni una oferta ni solicitud de transacción con instrumentos financieros ni promociones financieras no solicitadas.

Cualquier contenido de terceros, así como el contenido preparado por XM, como por ejemplo opiniones, noticias, investigaciones, análisis, precios, otras informaciones o enlaces a sitios de terceros que figuran en este sitio web se proporcionan “tal cual”, como comentarios generales del mercado y no constituyen un asesoramiento en materia de inversión. En la medida en que cualquier contenido se interprete como investigación de inversión, usted debe tener en cuenta y aceptar que dicho contenido no fue concebido ni elaborado de acuerdo con los requisitos legales diseñados para promover la independencia en materia de investigación de inversiones y, por tanto, se considera como una comunicación comercial en virtud de las leyes y regulaciones pertinentes. Por favor, asegúrese de haber leído y comprendido nuestro Aviso sobre investigación de inversión no independiente y advertencia de riesgo en relación con la información anterior, al que se puede acceder aquí.

Advertencia de riesgo: Su capital está en riesgo. Los productos apalancados pueden no ser adecuados para todos. Por favor, tenga en cuenta nuestra Declaración de riesgos.