Cheniere Energy falls short of core profit estimates on lower LNG margins
Adds Cheniere's high level of LNG contracts and its confidence that recent court decisions won't hurt its ability to get plants built, in paragraphs 7-8 and 13
By Tanay Dhumal and Curtis Williams
Aug 8 (Reuters) -Cheniere Energy LNG.N fell short of its second-quarter core profit estimates on Thursday, as weaker margins hurt the liquefied natural gas (LNG) producer.
Lower natural gas prices NGc1, which are down about 16% this year due to higher global inventories and lower demand forecasts, hurt the company's LNG delivery margins.
LNG revenue fell to $3.04 billion in the quarter ended June 30 from $3.92 billion a year earlier, and Cheniere's adjusted core profit of $1.32 billion missed an average analyst estimate of $1.35 billion as compiled by LSEG.
Cheniere's marginally raised full-year core profit forecast of between $5.7 billion and $6.1 billion, up from $5.5 billion to $6 billion previously, also came below analysts' expectations of $6.01 billion at midpoint, according to LSEG data.
The company, however, said it had a more constructive outlook for the remainder of the year, betting on higher demand from Asia.
"Cheniere continues to execute on its capital return strategy through its share repurchase and previously announced dividend. LNG should perform in line with the broader group on generally inline quarterly results and full-year expectations," RBC Capital Market analyst Elvira Scotto said.
Cheniere has been successful in getting companies to sign long-term offtake agreements and if approved it can contract all the LNG from its proposed Corpus Christi midscale expansion, paving the way for construction of trains 8 and 9 and debottlenecking, said its Chief Financial Officer, Zach Davis on an earnings call on Thursday.
Contracts signed between Cheniere and firms like Portugal's Galp GALP.LS may be enough to even reach a financial go ahead for the first phase of expansion at its Sabine Pass plant, said Davis.
Cheniere's Corpus Christi Stage 3 project, an export facility in South Texas, is progressing ahead of schedule, and was 62.4% complete as of June 30.
First gas into Train 1 of the project is expected in the next couple of months, with first LNG still projected by the end of the year, and LNG from the three Trains in 2025, said Cheniere President Jack Fusco on the earnings call.
Cheniere was able to do its major maintenance turnaround work on both its Sabine Pass and Corpus Christi plants without any major outage, which will help make up for lost LNG supplies experienced during the freeze in early 2024, said Fusco.
The Stage 3 project is expected to add 10 million metric tons per annum (mtpa) of LNG to Cheniere's production capacity of 15 mtpa at the Corpus Christi export facility.
Cheniere is not worried about recent U.S. court rulings that effectively ended the Federal Energy Regulatory Agency's (FERC) approval for two LNG export projects, as Cheniere had no ongoing court cases on its producing plants and is very detailed in the way it goes about navigating the regulatory process, said Fusco.
Financial firm Tudor Pickering Holt said the results were positive even though Cheniere suffered from reduced core profit due to lower margins.
"We view the print as a positive with projects progressing and feed gas expected at Stage Three, combined with their guidance increase," TPH said in a morning note to clients.
Cheniere's business and products are bi-partisan, since it promotes energy independence, benefits international trade, and LNG transcends any election cycle, said Fusco, who said Cheniere expects to maintain its Washington relationships regardless of who wins the U.S. presidential election.
Reporting by Tanay Dhumal in Bengaluru and Curtis Williams in Houston; Editing by Jonathan Oatis and David Holmes, Kirsten Donovan
Související aktiva
Poslední novinky
Zřeknutí se odpovědnosti: Subjekty skupiny XM Group poskytují služby a přístup do naší online obchodní platformy v režimu „execution-only”, což osobám umožní prohlížet a/nebo použít obsah, dostupný zde nebo prostřednictvím webové stránky, který není určený ke změně nebo šíření. Na takový přístup a použití se vždy vztahují: (i) Všeobecné obchodní podmínky; (ii) Upozornění na rizika; a (iii) Úplné zřeknutí se odpovědnosti. Takový obsah je proto poskytovaný pouze jako obecné informace. Mějte především na paměti, že obsah naší online obchodní platformy není ani žádostí, ani nabídkou vstupu do jakýchkoliv transakcí na finančních trzích. Obchodování na jakémkoliv finančním trhu zahrnuje významnou úroveň rizika pro váš kapitál.
Veškerý materiál, zveřejněný na naší online obchodní platformě, je určený pouze pro vzdělávací/informační účely a neobsahuje ani by neměl být považovaný za finanční, investiční, daňové nebo obchodní rady a doporučení, ani záznamy o našich obchodních cenách, nebo nabídku transakce s jakýmikoliv finančními instrumenty, či nevyžádadnou propagaci pro vaši osobu.
Jakýkoliv obsah třetích stran a také obsah, připravený společností XM, jako jsou názory, novinky, výzkum, analýzy, ceny, další informace nebo odkazy na webové stránky třetích stran, které jsou zobrazeny na tomto webu, jsou poskytovány v neupravené verzi jako obecný tržní komentář, a nepředstavují investiční radu. Pokud je jakýkoliv obsah uváděný jako investiční výzkum, musíte si uvědomit a přijmout, že tento obsah nebyl určený a nebyl připravený v souladu se zákonnými požadavky, vytvořenými pro podporu nezávislosti investičního výzkumu, a jako takový by měl být podle příslušných zákonů a předpisu považovaný pouze za marketingovou komunikaci. Ujistěte se, že jste si přečetli a plně rozumíte našemu Oznámení o seznámení se s riziky a investičním výzkumu, který není nezávislý, týkající se výše uvedených informací, a ke kterým lze přejít zde.