Dominion planning to power 15 more data centers in 2024



<html xmlns="http://www.w3.org/1999/xhtml"><head><title>UPDATE 2-Dominion planning to power 15 more data centers in 2024</title></head><body>

Receiving bigger power requests from data center developers

Moving forward with Virginia offshore wind despite lawsuit

Net income 78 cents per share in Q1, down from year ago $1.15

Sticks with 2024 operating EPS forecast range of $2.62 to $2.87.

Adds data center details and executive quotes in paragraphs 3, 4, 7, 8 and 9. Adds offshore wind details in paragraph 11

May 2 (Reuters) - DominionEnergy D.N expects to service 15 more data centers through the end of 2024 as the utility receives bigger power requests from computer warehouse developers, executives said on Thursday.

Dominion's service territory includes northern Virginia, which includes a cluster of counties thathold the world's largest concentration of data centers.

"The way data centers are ramping up is faster than they have before and their requests are bigger than they've been before," Dominion CEO Robert Blue said, adding that his company has connected 94 gigawatts of data center capacity in the past five years.

Data centers are computer warehouses, which are increasingly used for generative artificial intelligence, that consume vast amounts of electricity for their high-intensity computing and cooling systems.

After historically requesting electricity capacity demand of about 30 megawatts (MW), data center developers are now requesting two to three times that amount, Dominion executives said on a call following first quarter earnings.

Projects with multiple data centers can require several gigawatts of capacity. A single gigawatt can power about 750,000 homes.

Data centers used to typically take four to five years to ramp up to the full capacity they had contracted for with Dominion, Chief Operating Officer Diane Leopold said. Currently, full capacity could be reached in closer to two or three years, she said.

Data centers, which are driving U.S. electricity consumption out of a roughly two-decade lull, have recently come under scrutiny for their voracious energy appetite .

The proliferation of the centers has threatened to destabilize power grids and result in the prolonged use of carbon-emitting power sources like coal and natural gas, which can provide around-the-clock power in the way renewable sources like wind and solar cannot.

In its renewable energy plans, Dominionsaid it is moving forward with its Virginia offshore windfarm on time and on budget despite a recent lawsuit over environmental concerns, including the threat the project may have to whales and other marine wildlife.

The roughly 2,600-MW offshore wind development is 28% complete and recently received its 11th and final federal permit, executives said. Construction on the in-water and onshore part of the project is ongoing, with the installation of monopiles expected to begin next week.

The company reported an unfavorable weather impact of 6 cents per share on its utility earnings for the first quarter.It also said its interest and related charges rose nearly 20% to $574 million in the quarter, from $479 million a year earlier.

Interest rates in the U.S. have been at multi-decade highs since hikes began in 2023, leading to a higher cost of borrowing.

Dominion, which has about 6 million customers in 15 states, reported a net income of $674 million, or 78 cents per share, from $981 million, or $1.15 per share in the first quarter a year earlier.

Its operating revenue also fell to $3.63 billion, compared with $3.88 billion a year earlier.

The Richmond, Virginia-based company reaffirmed its 2024 operating earnings per share forecast in the range of $2.62 to $2.87.



Reporting by Laila Kearney in New York and Roshia Sabu in Bengaluru; Editing by Krishna Chandra Eluri and Elaine Hardcastle and Marguerita Choy

</body></html>

Disclaimer: The XM Group entities provide execution-only service and access to our Online Trading Facility, permitting a person to view and/or use the content available on or via the website, is not intended to change or expand on this, nor does it change or expand on this. Such access and use are always subject to: (i) Terms and Conditions; (ii) Risk Warnings; and (iii) Full Disclaimer. Such content is therefore provided as no more than general information. Particularly, please be aware that the contents of our Online Trading Facility are neither a solicitation, nor an offer to enter any transactions on the financial markets. Trading on any financial market involves a significant level of risk to your capital.

All material published on our Online Trading Facility is intended for educational/informational purposes only, and does not contain – nor should it be considered as containing – financial, investment tax or trading advice and recommendations; or a record of our trading prices; or an offer of, or solicitation for, a transaction in any financial instruments; or unsolicited financial promotions to you.

Any third-party content, as well as content prepared by XM, such as: opinions, news, research, analyses, prices and other information or links to third-party sites contained on this website are provided on an “as-is” basis, as general market commentary, and do not constitute investment advice. To the extent that any content is construed as investment research, you must note and accept that the content was not intended to and has not been prepared in accordance with legal requirements designed to promote the independence of investment research and as such, it would be considered as marketing communication under the relevant laws and regulations. Please ensure that you have read and understood our Notification on Non-Independent Investment. Research and Risk Warning concerning the foregoing information, which can be accessed here.

Risk Warning: Your capital is at risk. Leveraged products may not be suitable for everyone. Please consider our Risk Disclosure.